PLACING & COMPACTION OF CONCRETE

The successful placing and compaction of concrete can be achieved only if there has been careful forethought and planning. Because they are done almost simultaneously, placing and compaction are interdependent, and the two operations need to be considered together. The rate of delivery of the concrete should match the rate at which the concrete can be both placed and compacted.

The consistence of the concrete at the point of placing needs to suit both the placing technique and the means of compaction available.

Placing

Before concrete placing begins, the insides of the forms should be inspected to make sure they are clean and have been treated with release agent. If the forms are deep, temporary openings and lighting may have to be provided for this inspection. Rubbish, such as sawdust, shavings and reinforcement tying wire, should bblown out with compressed air. Any rainwater at the bottom of the form should be removed. Similarly, the reinforcement should be inspected to see that it complies with the drawings, and that the correct spacers have been used and there are enough of them.

The main objective with placing is to deposit the concrete as close as possible to its final position, quickly and efficiently and in such a way that segregation is avoided (Figure 17). Moving the concrete with poker vibrators should generally be avoided.

Particular care is necessary when using a skip for placing in thin walls and other narrow sections in order to avoid heaps and sloping layers. The skip discharge needs to be carefully controlled and the skip moved so that a ribbon of concrete is placed. The concrete should be placed in uniform layers not more tha500 mm thick or less, depending on the length of the poker blade. Otherwise compaction may be impeded by the weight of concrete on top. Provided that the concrete has been well designed and proportioned and is sufficiently cohesive, there is generally nneed to restrict the height from which the concrete is dropped. This assumes that the concrete is unimpeded and does not ricochet off formwork or reinforcement, which may cause segregation of the mix.

In deep lifts of columns and walls, delays and interruptions should be avoided to prevent colour variations on the surfaces; the rate should exceed 2 m height per hour. The correct rate of rise will have been calculated by the temporary works coordinator and must be observed in the interests of avoiding excessive formwork pressure and achieving  satisfactory surface finish. On columns and walls, care should be taken so that the concrete does not strike the face of the formwork, otherwise the surface finish may be affected; care also needs to be taken to avoid displacing reinforcement or ducts and to ensure that the correct cover is maintained.


Compaction
After concrete has been mixed, transported and placed, it contains entrapped air in the form of large voids. The object of compaction is to get rid of as much of this air as possible. Before compaction, concrete of consistence class S2 may contain 5% entrapped air, while concrete of S1 consistence class may contain as much a20%.

If this entrapped air is not removed by proper compaction the presence of these large voids will:
  •   Reduce the strength of the concrete - more than 5% loss of strength for every 1 % air
  •  Increase the permeability and hence reduce the durability and protection to the reinforcement
  •    Reduce the bond between concrete and reinforcement
  •   Result in visual blemishes such as excessive blowholes and honeycombing on formed surfaces
  • Fully compacted concrete will be dense, strong, impermeable and durable.


Vibration
Most concrete is compacted by means of internal poker vibrators that 'fluidize' the concrete and permit the entrapped air to rise to the surface. Pokers vary in size, usually from 25 - 75 mm in diameter. Table 13 gives a broad indication of poker sizes, and their characteristics and typical applications.

The radius of action will determine the spacing and pattern of insertions. As a guide, a spacing up to 500 mm centres is about right for a 60 mm diameter poker with concrete of medium consistence (see Table).

The poker should be inserted vertically and quickly and should penetrate some 100 mm into any previous layer; thereby stitching the two layers together. It should remain in the concrete until the air bubbles cease to come to the surface. Figures 18, 19 and 20 illustrate the process.

Being able to judge when the concrete has been fully compacted is largely a matter of experience. Sometimes the sound can be useful indicator, in that the pitch (whine) becomes constant when the concrete is compacted. In addition, a thin film of glistening mortar on the surface is a sign that the concrete is compacted, ais cement paste showing at the junction between the concrete and the formwork. The poker should be withdrawn slowly so that the concrete can flow back into the space occupied by the poker.

External vibrators are occasionally used, but their usefulness is limited on site by the heavy formwork needed to resist the stresses and shaking they produce. Their use is mainly confined to precast concrete elements, but they may be necessary for heavilreinforced walls and the webs of deep beams where it is difficult or impossible to insert a poker.

Table :  Characteristics and uses of internal poker vibrators.

Diameter of head
(mm)
Radius of action
(mm)

Approximate rate of compaction, assuming rapid placing
(m3/h)

Uses
20-3 0 (needle)
80 - 150

0.8- 2
Concrete with class S3 consistence and above in very thin sections and confined places. May be needed in conjunction with larger vibrators where reinforcement, ducts and other obstructions cause congestion
35-4 0
130-25 0
2- 4
Concrete with S2 consistence and above in slender columns and walls and confined places
50-7 5
180-35 0
3- 8
Concrete with class S1 consistence and above in general construction free from restrictions and congestion

Slabs are best consolidated by vibrating beam compactors. These combine the action of a screed and a vibrator, but they are only effective for a limited depth. In general, a slab more than 150 mm thick should be compacted with poker vibrators and finished with a vibrating beam. The edges of all slabs butting up to side forms should always be poker vibrated. Construction joints need particular attention (see the next section).

Over-vibration
The dangers and problems arising from under-vibration are far greater than any supposedly arising from over-vibration, since it is virtually impossible to over-vibrate a properly designed and proportioned concrete.

Re-vibration
Provided that it is still workable, no harm will be done if concrete that has already been compacted is re-vibrated. In fact, tests have shown that the strength is likely to be slightly increased.

Re-vibration of the top 75 - 100 mm of deep sections can minimize plastic settlement cracks or close them if they have been seen to develop.

Similarly, the re-vibration of the tops of columns and walls can often reduce the tendency of blow-holes to occur in the to600 mm or so.

Artikel Terkait